Cornish Metals to Bring Forward Refurbishment of New Cook’s Kitchen Shaft

VANCOUVER, British Columbia, March 04, 2024 (GLOBE NEWSWIRE) — Cornish Metals Inc. (AIM/TSX-V: CUSN) (“Cornish Metals” or the “Company”), a mineral exploration and development company focused on advancing the South Crofty tin project (“South Crofty” or the “Project”) located in Cornwall, United Kingdom, to a construction decision, reports that, after assessment of the condition of the shaft timbers in New Cooks Kitchen (“NCK”) shaft, it has decided to commence refurbishment of the shaft ahead of schedule.

Accordingly, and further to the announcement made by the Company on 13 December 2023, the proceeds raised from the offering completed in May 2022 will be re-allocated to accommodate the refurbishment of the NCK shaft, details of which are set out below.

Key Points:

Richard Williams, CEO and Director of Cornish Metals, stated: “Cornish Metals is committed to safe, efficient and cost-effective work practises and has, accordingly, brought forward the refurbishment of NCK shaft. This is a key milestone for the project and demonstrates the confidence both we as a Company and our largest shareholders have in the future of South Crofty. Importantly, management believes the project remains on track for production by the end of 2026.”

ABOUT CORNISH METALS

Cornish Metals is a dual-listed company (AIM and TSX-V: CUSN) focused on advancing the South Crofty high-grade, underground tin Project through to a construction decision, as well as exploring its additional mineral rights, all located in Cornwall, United Kingdom.

An updated Mineral Resource was completed in September 2023 with a 39% increase in tonnes and 32% increase in contained tin in the Indicated category for the Lower Mine (see news release dated September 13, 2023) as summarised below:

South Crofty Summary (JORC 2012) Mineral Resource Estimate
Area Classification Mass
(kt)
Grade Contained Tin /
Tin Equivalent
(kt)
Lower Mine Indicated 2,896 1.50% Sn 43.6
Inferred 2,626 1.42% Sn 37.4
Upper Mine Indicated 260 0.99% SnEq 2.6
Inferred 465 0.91% SnEq 4.2

The Mineral Resource Estimate for South Crofty is available in a report titled “South Crofty Tin Project – Mineral Resource Update NI 43-101 Technical Report”, dated October 27, 2023, co-authored by Mr. N. Szebor (MCSM, MSc, BSc, CGeol, EurGeol, FGS) and Mr. R. Chesher (FAusIMM(CP), RPEQ, MTMS) of AMC Consultants, and can be accessed through the above link and on the Company’s SEDAR+ page.

TECHNICAL INFORMATION

The technical information in this news release has been compiled by Mr. Owen Mihalop who has reviewed and takes responsibility for the data and geological interpretation. Mr. Owen Mihalop (MCSM, BSc (Hons), MSc, FGS, MIMMM, CEng) is Chief Operating Officer for Cornish Metals Inc. and has sufficient experience relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined under the JORC Code (2012) and as a Qualified Person under NI 43-101 and AIM. Mr. Mihalop consents to the inclusion in this announcement of the matters based on his information in the form and context in which it appears.

ON BEHALF OF THE BOARD OF DIRECTORS

“Richard D. Williams”
Richard D. Williams, P.Geo

For additional information please contact:

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Caution regarding forward looking statements

This news release contains certain “forward-looking information” and “forward-looking statements” (collectively, “forward-looking statements”). Forward-looking statements include predictions, projections, outlook, guidance, estimates and forecasts and other statements regarding future plans, the realisation, cost, timing and extent of mineral resource or mineral reserve estimates, estimation of commodity prices, currency exchange rate fluctuations, estimated future exploration expenditures, costs and timing of the development of new deposits, success of exploration activities, permitting time lines, requirements for additional capital and the Company’s ability to obtain financing when required and on terms acceptable to the Company, future or estimated mine life and other activities or achievements of Cornish Metals, including but not limited to: mineralisation at South Crofty, mine dewatering expectations, Cornish Metals’ exploration drilling programme, exploration potential and project growth opportunities for the South Crofty tin project and other Cornwall mineral properties and the timing thereof, timing and results of Cornish Metals’ feasibility study, the Company’s ability to evaluate and develop the South Crofty tin project and other Cornwall mineral properties, strategic vision of Cornish Metals and expectations regarding the South Crofty mine, timing and results of projects mentioned. Forward-looking statements are often, but not always, identified by the use of words such as “seek”, “anticipate”, “believe”, “plan”, “estimate”, “forecast”, “expect”, “potential”, “project”, “target”, “schedule”, “budget” and “intend” and statements that an event or result “may”, “will”, “should”, “could”, “would” or “might” occur or be achieved and other similar expressions and includes the negatives thereof. All statements other than statements of historical fact included in this news release, are forward-looking statements that involve various risks and uncertainties and there can be no assurance that such statements will prove to be accurate and actual results and future events could differ materially from those anticipated in such statements.

Forward-looking statements are subject to risks and uncertainties that may cause actual results to be materially different from those expressed or implied by such forward-looking statements, including but not limited to: risks related to receipt of regulatory approvals, risks related to general economic and market conditions; risks related to the availability of financing; the timing and content of upcoming work programmes; actual results of proposed exploration activities; possible variations in Mineral Resources or grade; outcome of the current Feasibility Study; projected dates to commence mining operations; failure of plant, equipment or processes to operate as anticipated; accidents, labour disputes, title disputes, claims and limitations on insurance coverage and other risks of the mining industry; changes in national and local government regulation of mining operations, tax rules and regulations. The list is not exhaustive of the factors that may affect Cornish’s forward-looking statements.

Cornish Metals’ forward-looking statements are based on the opinions and estimates of management and reflect their current expectations regarding future events and operating performance and speak only as of the date such statements are made. Although the Company has attempted to identify important factors that could cause actual actions, events or results to differ from those described in forward- looking statements, there may be other factors that cause such actions, events or results to differ materially from those anticipated. There can be no assurance that forward-looking statements will prove to be accurate and accordingly readers are cautioned not to place undue reliance on forward-looking statements. Accordingly, readers should not place undue reliance on forward-looking statements. Cornish Metals does not assume any obligation to update forward-looking statements if circumstances or management’s beliefs, expectations or opinions should change other than as required by applicable law.