Euro Manganese Reports Fourth Quarter and Year-End 2023 Financial Results and Project Developments

VANCOUVER, British Columbia, Dec. 14, 2023 (GLOBE NEWSWIRE) — Euro Manganese Inc. (TSX-V and ASX: EMN; OTCQX: EUMNF; Frankfurt: E06) (the “Company” or “EMN”) is pleased to announce key developments during the fourth fiscal quarter 2023 and to date. The Company has now filed its September 30, 2023 year-end Financial Statements, Management’s Discussion and Analysis, and other financial reports.

Key Developments During and Subsequent to the Quarter

Chvaletice Project, Czech Republic

Offtake Process

Bécancour Facility, Quebec, Canada

Financial Position

Dr. Matthew James, President & CEO of Euro Manganese, commented:

“We continued to deliver to plan in 2023 and achieved several key milestones during and subsequent to the fourth fiscal and calendar quarter. Our Team successfully produced on-spec HPMSM from our Demonstration Plant, advanced ESIA permitting, and completed a significant land-lease agreement, which provides us with access to approximately 60% of the Project’s manganese Reserves and overall, secures land access to roughly 85% of Reserves. Outstanding land rezoning requirements were also completed.

The Chvaletice Project received high-level inter-governmental support during the fourth calendar quarter by being named as a project under the Minerals Security Partnership. We aim to leverage opportunities to meet with private sector financiers partnering with the MSP as we advance with Project financing.

We were very pleased to announce the non-dilutive US$100 million funding package with Orion in late November. The proceeds from the initial US$20 million tranche allow us to further advance the Project, particularly completing permitting, initiating the FEED phase of the EPCM contract, and commissioning of the Demonstration Plant. We remain focused on delivering on these items, in addition to continuing negotiations with potential customers to enter offtake contracts and initiating the project finance debt process.

I am proud of the ongoing commitment of our Team to advance the Chvaletice Project and look forward to continued delivery of key catalysts in 2024 and beyond. Together, we are moving closer to our vision of being a leading and environmentally responsible producer of high-purity manganese.”

Q4 and Year-End 2023 Conference Call Details

Euro Manganese will host two separate Fourth Quarter and Year-End 2023 conference calls to serve stakeholders in their respective time zones. Content of both calls will be the same. Replays and transcripts of both calls will be available on Euro Manganese’s website: www.mn25.ca


About Euro Manganese Inc.

Euro Manganese is a battery materials company focused on becoming a leading producer of high-purity manganese for the electric vehicle industry. The Company is advancing development of the Chvaletice Manganese Project in the Czech Republic and exploring an early-stage opportunity to produce battery-grade manganese products in Bécancour, Québec.

The Chvaletice Project is a unique waste-to-value recycling and remediation opportunity involving reprocessing old tailings from a decommissioned mine. It is also the only sizable resource of manganese in the European Union, strategically positioning the Company to provide battery supply chains with critical raw materials to support the global shift to a circular, low-carbon economy.

Euro Manganese is dual listed on the TSX.V and the ASX, and is also traded on the OTCQX.

Authorized for release by the CEO of Euro Manganese Inc.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) or the ASX accepts responsibility for the adequacy or accuracy of this release.

Inquiries  
Dr. Matthew James Louise Burgess
President & CEO Senior Director, Investor Relations & Communications
mjames@mn25.ca lburgess@mn25.ca
  +1 (604) 312-7546

Company Address

#709 -700 West Pender Street
Vancouver, British Columbia, Canada, V6C 1G8   www.mn25.ca

Forward-Looking Statements

Certain statements in this news release constitute “forward-looking statements” or “forward-looking information” within the meaning of applicable securities laws. Such statements and information involve known and unknown risks, uncertainties and other factors that may cause the actual results, performance or achievements of the Company, its Chvaletice mineral project, its proposed Bécancour Plant or industry results, to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements or information. Such statements can be identified by the use of words such as “may”, “would”, “could”, “will”, “intend”, “expect”, “believe”, “plan”, “anticipate”, “estimate”, “scheduled”, “forecast”, “predict” and other similar terminology, or state that certain actions, events or results “may”, “could”, “would”, “might” or “will” be taken, occur or be achieved.

Regarding the Chvaletice Project, forward-looking information or statements include, but are not limited to, statements regarding the ability of the Company to deliver on samples meeting specifications to potential customers from the demonstration plant, the timing for FEED under the EPCM contract, final investment decision, ESIA approval and other various regulatory approvals, statements regarding the ability of the Company to obtain remaining surface rights and various permits, the benefits of remediating the historic tailings areas, statements regarding the expectation of the Company that the net proceeds from the first tranche of the Convertible Loan Facility will be sufficient funding to complete the permitting of the Chvaletice mineral project, complete the commissioning of the demonstration plant and its operation, initiation of FEED, complete the acquisition of certain land parcels needed for the Project, and certain site preparation works, and for general and administration expenses for more than 12 months; the growth and development of the high purity manganese products market, the desirability of the Company’s products, the ability of the Company to enter into binding offtake agreements with potential customers on favorable terms or at all, the growth of the EV industry, the use of manganese in batteries, the manganese project supply line, support from European financial institutions and any government funding, any anticipated benefits from legislation and the Company’s ability to obtain financing.

Regarding the Bécancour Plant, forward-looking statements include, but are not limited to, statements concerning the Company’s plans for advancing the Bécancour Plant and results of the Scoping Study including estimates of internal rates of return, net present values, and estimates of costs. Such forward-looking information or statements also include, but are not limited to, statements regarding the timing for completion of the Bécancour feasibility study, the Company’s ability to reach a definitive agreement with MMC to supply feedstock, the Company’s ability to operate the Bécancour Plant and associated production , the projected growth of the North American demand for high-purity manganese products, any benefits of legislation, the Company’s ability to secure offtake from North American customers, the Company’s ability to raise the necessary financing, and the timing of any permit application submissions and approvals and continuing successful cooperation with the W8banaki Nation.

Readers are cautioned not to place undue reliance on forward-looking information or statements. Forward-looking statements are subject to a number of risks and uncertainties that may cause the actual results of the Company to differ materially from those discussed in the forward-looking statements and, even if such actual results are realized or substantially realized, there can be no assurance that they will have the expected consequences to, or effects on, the Company.

Factors that could cause actual results or events to differ materially from current expectations include, among other things for the Chvaletice Project, lack of sufficient funding; the ability to develop adequate processing capacity and production; the availability of equipment, facilities, and suppliers necessary to complete development; the cost of consumables and extraction and processing equipment; risks and uncertainties related to the ability to obtain, amend, or maintain necessary licenses, or permits, risks related to acquisition of surface rights; the potential for unknown or unexpected events to cause contractual conditions to not be satisfied; the failure of parties to contract with the Company to perform as agreed; risks and uncertainties related to the accuracy of mineral resource and reserve estimates, variations in rates of recovery and extraction, the price of HPEMM and HPMSM, power supply sources and price, reagent supply resources and prices, future cash flow, total costs of production, and diminishing quantities or grades of mineral resources and reserves; the inability to secure sufficient offtake agreements; the inability to meet conditions under the Company’s secured credit facility and risks related to granting security; a delay or inability to get the ESIA approved by relevant authorities; unexpected results or unsuccessful completion of the various stages of the EPCM contract; and changes in project parameters as plans continue to be refined. For the Bécancour Plant, factors include, among other things: assumptions in the scoping study not proving accurate over time and negatively affecting results; an inability to obtain financing, unanticipated operational difficulties including failure of the Bécancour Plant; cost escalation for reagents, labour, power and other cost increases; inability to secure key reagents; a delay or inability to obtain or maintain necessary licenses or permits; the potential for unknown or unexpected events to cause contractual conditions to not be satisfied; inability to complete feasibility study or other technical studies or unexpected results; and risks and uncertainties related to limited feedstock supply options.

Additional factors that could cause results or events to differ materially from current expectations include risks related to global epidemics or pandemics and other health crises; availability and productivity of skilled labour; risks and uncertainties related to interruptions in production; unforeseen technological and engineering problems; the adequacy of infrastructure; social unrest or war; the possibility that future results will not be consistent with the Company’s expectations; increase in competition, developments in EV battery markets and chemistries; risks related to fluctuations in currency exchange rates, changes in laws or regulations; and regulation by various governmental agencies and changes or deterioration in general economic conditions. For a further discussion of risks relevant to the Company, see “Risk Factors” in the Company’s annual information form for the year ended September 30, 2023, available on the Company’s SEDAR+ profile at www.sedarplus.ca.

All forward-looking statements are made based on the Company’s current beliefs as well as various assumptions made by the Company and information currently available to the Company. In general, these include that the Company can achieve its goals; that the political and community environment in which the Company operates in will continue to support its projects; the Company can meet its obligations under the Convertible Loan Facility and secure additional financing, and assumptions related to the factors set out herein.

Although the forward-looking statements contained in this news release are based upon what management of the Company believes are reasonable assumptions, the Company cannot assure investors that actual results will be consistent with these forward-looking statements. These forward-looking statements are made as of the date of this news release and are expressly qualified in their entirety by this cautionary statement. Subject to applicable securities laws, the Company does not assume any obligation to update or revise the forward-looking statements contained herein to reflect events or circumstances occurring after the date of this news release.

1 Euro Manganese cautions that the Study does not constitute a scoping study within the definition used by the Canadian Institute of Mining, Metallurgy and Petroleum (“CIM”), as it relates to a standalone industrial project and does not concern a mineral project of the Company. As a result, disclosure standards prescribed by National Instrument 43-101 – Standards of Disclosure for Mineral Projects (“NI-43-101”) are not applicable to the scientific and technical disclosure in the Study. Any references to Scoping Study or Feasibility Study by Euro Manganese in relation to the Bécancour Plant are not the same as terms defined by the CIM Definition Standards and used in NI 43-101.

 


Bay Street News